Calender and original durations
- Created
- 4
- 2
Hey,
Ive just set up a new project. For that project i have set up a calender where the working hours are 11hrs a day, 7 days a week. I have made this calender the activity and project default calender. I have also gone into user preferences and changed the work time to 11hrs per day.
However when i add a new activity, it automatically comes up with an 8hr duration as opposed to an 11hr duration. Also the times that are shown are 00.00 - 14.30 which isnt even 8 hours!! It should show 06:30 - 17:30 as per the calender. Obviously somethings going wrong, can anyone shed any light?
4 replies
Oldest firstLog in or join to reply