Skip to content

Planning Update in P6 vs P3

Cyril GALZINMember for 15 years
Created
0
2
0

Hello, i am used to update planning for EPC Projects in P3. I am starting using P6 and i have problem finding good configuration (Calculation rules, user preferences, ...) to get a good result for my progress which is based on actual unit.

I would  like to input a % progress which will calculate the actual unit from the budgeted unit. Remaining unit will be recalculated by Budgeted unit - actual unit. But I would like also that my finish date is defined as an expected finish date (not linked to my % progress).

This method was working well on P3 but apparently it's not possible with P6.

If anyone has an idea feel free ...

Thanks

Cyril

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?