Filter in primavera 6.7

Noor MananMember for 15 years
Created
3
1
0

Salaam, 

         Can any one help me,i want to see activities schedule to be completed on 30-10-2011 say.what is the method of this problem currently i am using primavera 6.7.please any one who have knowledge about this questen kindly send me urgent.My email is noormanan@gmail.com and i am will be very grateful for this act of kindness.

3 replies

Oldest first
  1. 0
    AB Timo ·

    Noor,Perform Following

    Noor,

    Perform Following Steps,

     

    1-Click On" Filter Icon "Or goto  View-->Filter

    2-Click "New"

    3-Write Filter name at the top

    4-in "Parameter" Column select "early Finish"

    5-in "is" Column select "is within the range of"

    6-in "Value" column select the Lower Date.

    7-in "High Value" column select the "Upper Date"

     

    For Example to want to filter from 1stOct 2011 to 10,October 2011,then lower value will be 01-10-2011 and upper value 10-10-2011.

    Regards,

  2. 0
    Noor Manan ·

    salaam dear,

    salaam dear,

                    currently i am using primavera6.7 but i don't know how can i find the EARLY FINISH date of the activities,For exam my project completion date is 07-12-2011 but some activies is finising early and my PM told me that i want to check the EARLY FINISH date on 15-11-2011.

    please any one who understand my problem kindly explane in short for me.my email is (noormanan@gmail.com).

    i am will  be very grateful in advance...... 

  3. 0
    AB Timo ·

    Noor,it is better to discuss

    Noor,

    it is better to discuss here rather than asking for the email.it helps many others beside you and that is how this forum ican be useful.

     

    Regarding your Question,

    The phrase early finish date (also known by the abbreviation EF) refers, on the critical path method, to the earliest possible point at which the as yet to be completed elements of a schedule activity (or, depending on the particular context, the entire project as a whole) may potentially be completed .

     

    You just need to add "Early Finish" olumn in your Activity Table.

    Regards,

    Faiz