How to Keep Resource Usage Profile Time Period Filter After Clicking on Activity Details

Christian GlorieuxMember for 14 years 11 months
Created
2
2
0

Hi All,

I have leveled my resources however they remain over allocated in some instances.  That said, I would like to know if it is possible to view the "resource usage profile", select a "time period" to display the respective activities for that resource(s), then go into the "activity details" to adjust allocated resources if applicable; however when I do this, the "activity filter" for the "time period" from the "reource usage profile" is lost when I click the "activity details" tab.  I was therefore looking for a way to keep that "time period" filter from the "resource usage profile" while I am in the "activity details" tab.  Any help on this would be much appreciated.  Thank you for your time and have a good day.

Regards,

Christian

2 replies

Oldest first
  1. 0
    Mohammad Mojahid Akhtar ·

    Dear if you want to see the

    Dear

    if you want to see the activity

    Click Project then activity

    go to column and create Resource IDs column

    then go filter

    Display all rows Parameter Is Value High Value

                          Parameter                      is                          value
      Where          Resource IDs                   contains                TL 
     

    you will get what you want.

  2. 0
    Christian Glorieux ·

    Hi Mohammad,Thank you for

    Hi Mohammad,

    Thank you for your help.  I have used your concept in principal by creating an activity code and filtering it out and it works however I would be interested in understanding your method detailed above.  Currently I have resource ID's allocated to each resource assigned however what does the Value "TL" mean?  I tried to create a filter as you mentioned above however no results were derived when I applied it.  Please let me know your thoughts when you get a chance.  Thank you for your time and have a good day.

    Regards,

    Christian