Moving Activities Between Projects

Kris DurbinMember for 14 years 11 months
Created
4
2

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Chris If I were doing this

    Hi Chris

    If I were doing this in Asta PowerProject I would set up the first two projects and add the inter project links - I assume these are standard for each project.

    I would then copy these two to make four projects and again set up the inter project links tp make a block of four.

    By copying and pasting these blocks from four to eight to sixteen etc it will not be long before the whole set is linked up.

    Best regards

    Mike Testro

  2. 0
    Shah. HB ·

    Hi Kris DurbinIn P6.7 you

    Hi Kris Durbin

    In P6.7 you have an option to move WBS between projects which helps to fix your issue

     

    Regards

    Shahul

  3. 0
    Rafael Davila ·

    Consider using Project

    Consider using Project Portfolios, the details are software specific and I use other software but this shall be the way to go.

    Good luck,

    Rafael

  4. 0
    Hannes de Bruyne ·

    Hi Kris what Shahul said is a

    Hi Kris

     

    what Shahul said is a very good option. Open all Projects, Change to the WBS-view and shift single branches to the required project (Right mouseclick on the very left side of the text-line)

    Another way is cut and paste instead of copy and paste (Ctrl-x, Ctrl-v), links will remain, activities or WBS-Branches are shiftet to the right project