Importing Activity Codes

Wasim ShahzadMember for 15 years 8 months
Created
6
2
0

HI,

Is there any way to import activity codes defined in excel. ??

6 replies

Oldest first
  1. 0
    D Artagnan ·

    Yes you can import activity

    Yes you can import activity code in excel. If you can find Project.xls (an SDK file), there's a sheet that does all that. I am just not in the office right now to send you the file.

  2. 0
    Wasim Shahzad ·

    I have that file. but it

    I have that file. but it explains you can only import the activity codes that are already defined in primavera.
    Please explain.

  3. 0
    Wasim Shahzad ·

    I am asking to import activiy

    I am asking to import activiy codes in Primavera from Excel..

  4. 0
    D Artagnan ·

    That file can do the export

    That file can do the export and import.

    1) First, check if you have SDK installed in your system. If not, install using your P6 installation CD.

    2) Open the Excel File (Project.xls), checl first if you can log-in. If you have a successful log, you must find all the projects lists.

    3) There is "Get Activity Codes" - for import from P6 to excel file and "Set Activity Codes" -  for export from excel file to P6.

    I am just not in the office to give you the snapshots.

  5. 0
    Wasim Shahzad ·

    Thanks i have the file just

    Thanks i have the file just let me check if this work.

    Tanks any way

  6. 0
    Wasim Shahzad ·

    Thanks..It works

    Thanks..

    It works