I have a project that I have imported from MSP.

 

I have 215 activites in which within this I have 7 sites.

Is it possible to replicate each site within my activities for 6 years. (example Site 1-activities associated with each. It shows the schedule from 2012 to 2013 and I want it to show the same activities within that site for

If this is possible how would I go about doing this?

 

Thanks

Rhys

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Hi Rhys,   Apologies if I'm

    Hi Rhys,

     

    Apologies if I'm being dense, but I have absolutely no clue what you are trying to achieve. -Could you have anothe go at explaining it?

     

    Cheers,

     

    G

  2. 0
    Rhys Parry ·

    Sorry Gary me and explaning

    Sorry Gary me and explaning sometimes don't go :)

     

    What it is I have activities that are sub headed as individual sites with activities associated with them.

    What I need to do is for each sub heading and their activities is replicate this for 6 years. So at the moment its from april 2012 to april 2013 for site A and Site B and Site C etc each having activities listed for them.

     

    I was thinking of copying the individual sub headings within the WBS six times.

    Does this seem like the correct solution.

    Hope that helps

    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?