Using the Fill Down Option In P6

Rhys ParryMember for 15 years 1 month
Created
4
3
0

I have a calender setup that is showing standard for all my activities and what I want is to change them all to a 7 day working week.

I have added the column calender in and then I chose one activity with the 7 day a week in it, but it is not allowing me to select that column and fill down to all the others. (Fill Down option is greyed out)

 

Any Ideas

Thanks

4 replies

Oldest first
  1. 0
    James Mulhearn ·

    You do not need to select the

    You do not need to select the column only the cell with the calendar info the hold the 'shift" key down and go to the cell at the bottom of the Calendar Column "click" on that cell and then fill down...

    P6 highlites every thing but only fills down the column you are in , hope this helps...

  2. 0
    Rhys Parry ·

    I got it working in the End

    I got it working in the End thanks I thought It was selecting all of the columns but as you said if I click on the column i want to fill down and highlight the other rows it just fills that column.

     

    All sorted

    Thanks

  3. 0
    Siddic K ·

    How to Change Activity ID in

    How to Change Activity ID in P6 without exporting to excel. Please help .....

  4. 0
    Nilkamal Parikh ·

    Hi Siddic,Please select all

    Hi Siddic,

    Please select all the activities which you want to change their IDs. Go to Edit and select renumber activity ids. You can see the manu which will allow you to change the activity ids by increasing its number, Auto number which you can assign what you want for new ids or just to replace beginning characters of your id.

    Hope this will help.

    Cheers

    Nilkamal Parikh

Log in or join to reply