Using the Fill Down Option In P6
In the Open Standard
Rhys ParryMember for 15 years 1 month
- Created
- 4
- 3
0
I have a calender setup that is showing standard for all my activities and what I want is to change them all to a 7 day working week.
I have added the column calender in and then I chose one activity with the 7 day a week in it, but it is not allowing me to select that column and fill down to all the others. (Fill Down option is greyed out)
Any Ideas
Thanks
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?