Resourse Loading

Arun VasanthMember for 17 years
Created
2
2
0

Friends 

While loading the resourses when I am entering the budgeted units the duration is changing ..

wats the reason???

Please help.

 

Rgards

Arun.V

2 replies

Oldest first
  1. 0
    Shah. HB ·

    Hi Arun Vasanth  It is due to

    Hi Arun Vasanth 

     

    It is due to duration type you assigned to each activity try by using option fixed duration and units 

     

    Cheers

    Shahul

  2. 0
    Arun Vasanth ·

    Thank you Shahul

    Thank you Shahul