Skip to content

changing original duration in resource tab won't work

Johnny PainMember for 21 years
Created
0
3
0

hi all,

I kinda have a problem linking original duration from the STATUS tab and the one in the RESOURCES tab in P6.2.1.

let's take a random task :

OD 4

UPT 200%

BQ 8

 

till now it's normal, but when I change the OD in the RESOURCE tab (it's not present by default but we can add it) because right now it's easier to assign a *new* duration in here, the BQ is updated but the OD in the STATUS tab isn't.

and it doesn't work in reverse either, when I change the OD in the STATUS (or in the column I just added), it doesn't update in the RESOURCE tab, and it doesn't even recalculate BQ.

 

the problem is, I discovered this problem after having typed lots of new durations so I'm kinda stuck !

 

FYI, every task is set to "Fixed duration & units/time" (we need that), and I'd like to think I tried every possible combination in the options tabs everywhere.

 

am I missing something ?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?