Resource Loading

Muhammad AsimMember for 15 years
Created
1
2
0

Hi:

What is resource loading in Primavera, and what is difference between resource loading and resource assigning?

1 reply

Oldest first
  1. 0
    Doug Young ·

    Hi Muhammad Asim, Resources

    Hi Muhammad Asim,

    Resources are assigned to tasks. Loading is the profiles for many tasks. Or loading can mean one tasks loaded by different curves, like front loading or back loading. This means the spend profiles are either linear,,,same each day, week or month. Or start small and work up,,or start big and reduce.

     

    I'm sure you've found this out by now. But I'm quite new to this, and keen to make contacts