Dear Planners,
Is there any one understand below message from Integrity checking?
2. Check Activity Resource Assignment for: Assignment with Price/Time = 0
>>>Warnings:
Activity Resource Assignment: O16C10000060, C.BS-PLF - Not Fixed: Please examine and correct the data manually.
Activity Resource Assignment: O16C10000070, C.BS-PLF - Not Fixed: Please examine and correct the data manually.
3.Check Activity Resource Assignment for: Assignment with resource Price/Time or Overtime Factor out of sync
>>>Warnings:
Activity Resource Assignment: O16C10000060, C.BS-PLF - Not Fixed: Please examine and correct the data manually.
Activity Resource Assignment: O16C10000070, C.BS-PLF - Not Fixed: Please examine and correct the data manually.
Thanks,
Matthew
1 reply