Updating the program

Arun VasanthMember for 17 years
Created
6
1
0

Dear Friends

After updating my base program .There is a delay of 29 days & it is showing only in the program.

But in the activities the maximum negative float is -25 only .Any one resolve this issue.....???

 

I will attach the picture

6 replies

Oldest first
  1. 0
    Mohamed Sallam ·

    Arun, This is due the

    Arun,

    This is due the difference between the global and project calendars. 

  2. 0
    Nithin Shetty ·

    Thanks Mohamed. This is of my

    Thanks Mohamed. This is of my interest too. Is there a way to show overall total float in the same project calender? Please advice. 

    e.g. it shows -25 instead of -29.

    Thanks.

  3. 0
    Arun Vasanth ·

    Thank you Mohamed  Then For

    Thank you Mohamed 

     

    Then For making one what I have to do????

    I have to consider the actual delay as 25 or 29 days???

  4. 0
    Mohamed Sallam ·

    Arun, In order to avoid the

    Arun,

    In order to avoid the difference, you may assign the Project calendar as default global calendar.

    To calculate delays, you should consider the difference between working days and calendar days.

    The variance - BL Project finish date should be considered, in that case the delay is 29 calendar days.

    Did I clarify your queries?

  5. 0
    Arun Vasanth ·

    Thank you Mohamed  In my Base

    Thank you Mohamed 

     

    In my Base program there are 2 calendors .

    1.6 day Calendor 

    2. 7 days calendor 

    Which one I have to make as default????

  6. 0
    D Artagnan ·

    I had the same problem. IMO,

    I had the same problem. IMO, if it's a milestone, use the 7 day calendar.

Log in or join to reply