P6 Cost % Complete - Clarifications on automated calculation

Nithin ShettyMember for 22 years 1 month
Created
3
4
0

Dear Team,

I have a query on the above subject. Please refer to the below snapshot.

 

Can anyone kindly explain me the formula for the P6 generated cost %tages as below.

1) %tage outlined with yellow rectangular box

2) %tage outlined with blue oval

3) %tage highlighted with cyan colour.

Thanks a lot in advance.

I really appreciate your answer.

Kind Regards,

Nith

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Nith,too bad your picture

    Nith,

    too bad your picture cannot be read

    Alexandre

  2. 0
    Nithin Shetty ·

    p6_query.jpgMy Apologies.

    My Apologies. Attached is the better size image.

     

    Appreciate any help.

  3. 0
    Raymund de Laza ·

    Hi, Cost % of Budget (%) Cost

    Hi,

    Cost % of Budget (%)

    Cost % of Budget threshold value is expressed as a percentage. An issue is generated if the ratio of the activity's actual cost to its budgeted cost (actual cost / budgeted cost * 100) falls beyond the threshold values.

    Actual cost is the same as Total Actual Cost, and original cost is the same as Budget at Completion (BAC).

    The Cost % of Budget will reach 100 percent when the actual cost reaches the budgeted cost. The Cost % of Budget may be greater than 100 percent.

     

Log in or join to reply