Auto compute actuals ?????
In the Open Standard
Yaser A. Al-BustanjiMember for 16 years 5 months
- Created
- 2
- 1
0
Dear Friends
I have a question about the above subject.
The function "Auto compute actual" under the details tab in resource workspace didn’t work when I put the function” Recalculate Actual Units and Cost when Duration % Complete Changes" checkbox on under calculation tab in project workspace.
I can’t understand the differences between these two options
Regards