Constraint on time?

Kath MurrayMember for 14 years 11 months
Created
1
3
0

Hey everyone i have been  searching for this and think the answer is no but just wanted to clarify..

Is there anyway to set a constraint on hours spent on an activity or do constraints only apply to dates?

Sorry if its a stupid question im quite new to Primavera

1 reply

Oldest first
  1. 0
    Ronald Winter ·

    Kath,   Just like any other

    Kath,

     

    Just like any other date in P6, you can specify hours and minutes as well as just a date for constraints.  If you do not specify a constraint time, then midnight (00:00) will automatically be assigned.  Select Edit / Users preferences to have P6 show the time as well as the date.

     

    As a reminder, all dates in P6 also include a time element.  You can choose to not see it but it is always present.  I recommend always showing the time unit to help prevent entry errors.  Good luck!

Log in or join to reply