Hi,
I am trying to resource/cost load a project.
I have 5 activities in various WBS that have 1 total cost. So I was told to use a level of effort and load the cost and resource onto the level of effort. This is exactly what I did. However, when I look at the loading curve of the LOE it loads the whole cost within the first month of the 6 month activity.
Does anyone know why this happens or how this can be fixed?
Thanks,