Is there a way to copy&paste activities between 2 opened projects in P6?

Ayman EleishMember for 15 years 9 months
Created
4
4
0

Dear All,

Is there a way to copy&paste activities between 2 opened projects in P6?without using WBS.

Regards,

4 replies

Oldest first
  1. 0
    Adrian Nicholas ·

    Ayman,   Just Open both

    Ayman,

     

    Just Open both Projects together and copy the activities you want and paste them on to the destination project that  you want it to go to.

     

     

    Cheers,

     

    Adrian N

  2. 0
    Adrian Nicholas ·

    Ayman,   Just Open both

    Ayman,

     

    Just Open both Projects together and copy the activities you want and paste them on to the destination project that  you want it to go to.

     

     

    Cheers,

     

    Adrian N

  3. 0
    Ayman Eleish ·

    Adrian, You are completely

    Adrian,

    You are completely right but that can not be done unless you organize the layout by WBS.

    Is there other method to do the same without organizing with WBS.

    Thanks,

  4. 0
    Sethupathy Subramaniam ·

    Greetings, Make sure of the

    Greetings, 

    Make sure of the following while copying and pasting activities between two open projects in P6

    1. the calendar assigned for the activities

    2. activity codes assigned (if any)

    recently i  faced these problem after copying when i checked the above things i found that the calendar for activities it took a global default calendar and activity codes were never really copied. Resource assignments were proper. 

     

    Regards

     

    Sethupathy

Log in or join to reply