Time Setting for Two Different Team

John PeterMember for 15 years 7 months
Created
3
2
0

Oh Hi guys 

 

I hope you have completed your Xmas shopping ....

I have a small team of civil designer and site team of workers

civil designers mostly work in office and they do 37.5 hr per week 

where as site staff do 40 hrs per week 

if i change time period to 37.5 hr per week in primavera than my site 8 hours activity shows me duration like 1d.5hr

and 40 hours as 5d2.5hr 

 

Any suggestion on this Issue

3 replies

Oldest first
  1. 0
    John Peter ·

    Thanks in Advanced for

    Thanks in Advanced for replies 

  2. 0
    Khaja Sharief ·

    Try creating two different

    Try creating two different resource calander one with 37.5h per week for civil designers and other 40h per week for site team. Assign these calenders to their respective activities. You should also set activity type as resource dependant and appropriate duration type either fixed units or fixed units/time.

    Cheers

  3. 0
    Rafael Davila ·

    John,I use different software

    John,

    I use different software but try using a 24/7 calendar for your Civil Designers, then assign a 37.5 hours per week calendar to your Office Design activities and a 40 hours per week calendar for your Site Design activities.

    By assigning a 24 hours 7 day per week calendar to your resource you will be able to assign different work hours to the work at the office and work at the field to the same designer.

    Photobucket

    Good luck,

    Rafael

Log in or join to reply