Time Setting for Two Different Team
In the Open Standard
John PeterMember for 15 years 7 months
- Created
- 0
- 3
0
Oh Hi guys
I hope you have completed your Xmas shopping ....
I have a small team of civil designer and site team of workers
civil designers mostly work in office and they do 37.5 hr per week
where as site staff do 40 hrs per week
if i change time period to 37.5 hr per week in primavera than my site 8 hours activity shows me duration like 1d.5hr
and 40 hours as 5d2.5hr
Any suggestion on this Issue