Skip to content

Time Setting for Two Different Team

John PeterMember for 15 years 7 months
Created
0
3
0

Oh Hi guys 

 

I hope you have completed your Xmas shopping ....

I have a small team of civil designer and site team of workers

civil designers mostly work in office and they do 37.5 hr per week 

where as site staff do 40 hrs per week 

if i change time period to 37.5 hr per week in primavera than my site 8 hours activity shows me duration like 1d.5hr

and 40 hours as 5d2.5hr 

 

Any suggestion on this Issue

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?