How to load resource for Lump sum contract in P-6.2
- Created
- 0
- 3
Hi,
My client instructed us to generate invoice through Primavera (Billing through Primavera P6) and my contract is
a lumsump contract. The contract value given in the Cost Center part has a list of items, the payment will be relased (by client) against the completion of the respective cost center items (to us). We dont have the seperate BOQ, So What I did is,
1. I just inroduce a seperate WBS as Cost Center in the master programme.
2. added the each cost center items as activities under the new WBS.
3. I linked the cost center items to the respective activities completion.
4. Then I loaded the the cost for the respective cost center items as budget units.
5. Then I update the Physical progress & I generate the invoce.
Please any body advice the above methodology is correct or suggest any other methodology .
Reg,
Sri
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?