Original duration

Luís Felipe Cazarim de SouzaMember for 14 years 9 months
Created
2
3
0

Dear All,

 

I have to update a Schedule but I am having a problem updating the original duration. In the image above for exemple in the activity "Planejamento" the Original duration is 37d but I need to change it.

Should it be the sum of the sucessors activity? How it is calculated? 

 

Look the image below

2 replies

Oldest first
  1. 0
    Paul Harris ·

    This is a summary value from

    This is a summary value from the activities below so you need to update your activities below.

     

    Paul E Harris
    Director Eastwood Harris Pty Ltd
    www.eh.com.au and  www.eastwoodharris.com
    www.primavera.com.au - this is a new Primavera Software resources web site.

  2. 0
    Marwan Hmood ·

    37 days, calculated from

    37 days, calculated from earliest activity start and finish dates. Updating summary OD must be done through updating activity OD.

     

    Regards,