Skip to content

Create Baseline & Update Schedule in P6 v7

Sahibzada MoqeemMember for 15 years 5 months
Created
5
2
0

Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

Thanks.

5 replies

Oldest first
  1. 0
    Sahibzada Moqeem ·

    Can anyone tell me the

     

    Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

    Thanks!

    At your Early response!

  2. 0
    Sahibzada Moqeem ·

    Still didn't receive any

    Still didn't receive any reply!!!!

  3. 0
    Johannes Vandenberg ·

    Hi SahibzadaIs this what you

     

    Hi Sahibzada

    Is this what you are looking for ?

    Try this; In P6 you have 3 steps to ensure that the baseline milestones are not shifting during updating the schedule.

    Step 1: Go to maintain baseline and add new baseline. Give the baseline and clear identification. Say BASELINE APRIL 2012

    Also make the BASELINE APRIL 2012 your PROJECT BASELINE. this is at the lower part of the same form

    Step 2: Go to Assign baseline and assign the baseline BASELINE APRIL 2012. 

    Step 3: Go to View bars and select the tick box for PROJECT BASELINE. 

    You should now see that the PROJECT BASELINE bar is displayed , usually in a yellow color, under the green colored bars.

    If you now update the schedule the yellow PROJECT BASELINE bars and milestones are remaining in the same position and the remaining duration bars these are color green are moving.

    In short, maintain the baseline, assign the baseline and display the baseline

    Johannes

  4. 0
    Mushtaque Ali ·

    MAINTAIN BASE LINE :First i

    MAINTAIN BASE LINE :

    First i am going to brief  you the Baseline can be create 

    • Current project as a Baseline
    • convert another project to new Base line       

    Step 1.  Go to Project and select from the drop down maintain baseline and press add button then new window will be appear there you can select either you want to add 1. Current Project as Base line or Convert another Project as New Baseline Choise is yours

     

     

    Step 2. Go to Project and select from the drop down Assign Baseline.

    Step 3. Go to View and and select from the drop down Bars and tick the Primary Base line under disply. You should now see the Project baseline bar is displayed, generally bar colour is in yellow you can change as per your wish.

  5. 0
    Mushtaque Ali ·

    Hope now your doubt is clear.

    Hope now your doubt is clear.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?