I am new to P6...  How to change the currency ?

I hope people will have patience to answer my questions?

 

 

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Go to "admin" menu

    Go to "admin" menu > currencies

    Choose "add" to set up your new currency

     

    Next go to "Enterprise" menu > resources

    When creating or ammending your resources, you can select which currency to use from the "details" tab