Skip to content

P6 Calculation fixed unit/Time

walid LahianiMember for 15 years 11 months
Created
5
3
0

GOood morning ,

This is the question

I changed the data date and pressed F9 =>the remaining duration didn't changed but at complete duration increased

I want that remaining duration change automatically so the remaining units in ressources increase and the formula


AT COMPLETE DURATION =Actual duration+Remaining duration still correct

thanks

5 replies

Oldest first
  1. 0
    Somasundaram K ·

    Schedule using Expected

    Schedule using Expected Finish date field. That should solve your problem. Thanks!

  2. 0
    Frederic Fasquelle ·

    Hi Somasundaram K,I jump of

    Hi Somasundaram K,

    I jump of your proposal and I would be interested to get any feedback.
    To update my project, I am filling "Expected Finish" field (only activity started).

    First consequence is to get FF=0 on this activty.

    Is there any other consequence in scheduling ?
    Is it a good practice to fill this field instead of modifying directly finish date ?


    regards

  3. 0
    Somasundaram K ·

    Yes, Am not aware of any

    Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

    Please let me know if this is not what you meant. Thanks!

  4. 0
    Somasundaram K ·

    Yes, Am not aware of any

    Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

    Please let me know if this is not what you meant. Thanks!

  5. 0
    Ravikumar Allada ·

    I would like to know how to

    I would like to know how to copy the budgeted  units activity wise on a weekly timescale in P6

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?