For what reasons would the Budget At Completion be different to the Budgeted Total Cost on an activity?

John SimsMember for 15 years 4 months
Created
4
2
0

For what reasons would the Budget At Completion be different to the Budgeted Total Cost on an activity? Primavera help says that these two fields should contain the same value. Currently this is giving discrepancies within our reporting run.
 

Any help would be great.

John

4 replies

Oldest first
  1. 0
    Amit Parmar (PMP) ·

    Hi John,Budget at Completion

    Hi John,

    Budget at Completion is the Total cost from the Baseline, BAC will be equal to Budgeted Total Cost till you do not add/delete more resources or costs in the current project. If you make changes to cost inn your current project then the values will not be equal to BAC.

    Thanks & Regards

    Amit 

     

    Check out my blog on Primavera at http://www.primaverablog.in
  2. 0
    John Sims ·

    Hi, thanks for your reply. As

    Hi, thanks for your reply.

    As you see from the picture below the bottom activity is showing two resources have been added to the activity but it is only showing the cost for one of them in the BL Project Labour Cost.

    The activity was added seperatly to the rest of the activities with both resources but i have updated the current baseline, so surely it should be the same cost has the Bugeted Labour Cost? 

    Any ideas why its not calculating both resources?

  3. 0
    Amit Parmar (PMP) ·

    Hi John,The image quality is

    Hi John,

    The image quality is too low for me to zoom in and have a look. Can you upload a better quality image so that i can read the words clearly.

    Thanks

    Amit

     

    Check out my blog on Primavera at http://www.primaverablog.in
  4. 0
    John Sims ·

    For what reasons would the

    For what reasons would the Budget At Completion be different to the Budgeted Total Cost on an activity? Primavera help says that these two fields should contain the same value. Currently this is giving discrepancies within our reporting run.
     

    Any help would be great.

    John