WBS not showing in Activity

Kath MurrayMember for 14 years 11 months
Created
9
3
0

Hiya

Im using Primavera P6 Project Management Release 7.0 SP2.

Today i have been trying to update various projects which require additional WBS. When i add the WBS it shows in that tab but when i move to Activities to add further activities the WBS is not showing up. I have tried various things checked dates etc but nothing is working just wondered if anyone else had come accross this problem before?

Thanks

9 replies

Oldest first
  1. 0
    Sm Pum ·

    kath murraymake check

    kath murray

    make check following

    1- Group & sort---> Group by----> WBS

    2- Group & Sort ---> make sure that "hide if empty" option is unchecked.

     

    Regards

  2. 0
    David Craig ·

    I have this same issue. I

    I have this same issue. I make sure the box is un-ticked but it still doesn't display the WBS in the activity window. This is irritating as much as it is time consuming. I'm sure it must be a bug within the software as it never used to behave like this
  3. 0
    Kath Murray ·

    Thanks the hide if empty

    Thanks the hide if empty option was checked so its fine now thanks again for your help!

    x

  4. 0
    Kath Murray ·

    David i now have noticed that

    David i now have noticed that each time i open Primavera it automatically checks the 'hide if empty' its a bit annoying i agree not sure why its doing that. If i manage to find out why then i will post back on here.

  5. 0
    Kath Murray ·

    David i now have noticed that

    David i now have noticed that each time i open Primavera it automatically checks the 'hide if empty' its a bit annoying i agree not sure why its doing that. If i manage to find out why then i will post back on here.

  6. 0
    David Craig ·

    Thanks kath!

    Thanks kath!
  7. 0
    Ahmad Ghidan ·

    Thanls so much 'SM PUM' it's

    Thanls so much 'SM PUM'
    it's worked 

  8. 0
    Rizwan Ea ·

    TNANK YOU SM PUM

    TNANK YOU SM PUM

  9. 0
    Rizwan Ea ·

    @Hiya Please follow SMPUM

    @Hiya Please follow SMPUM Post Step-1 & Step-2.