Doing new P6 planning

walid LahianiMember for 15 years 11 months
Created
2
3
0

Good morning,

I have a scope of work of one project ,

-I extract activities,durations,relationships,I do the WBS,OBS

-Now ,what type of progress I have to choice (physical or unit or or or...)

          what type of duration to choice

 how to do the update every week and where to store the historic (is it in doing many baslines???-every week)

How to update the progress ,is it on updating the ressource units....

How to do the weights...

I know it's many questions at one time ,you can respond to some and not to all :)

 

 

Thank you

          

         

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi Mr. Walid, You may need a

    Hi Mr. Walid,

    You may need a Private Tutor for all that queries........

  2. 0
    Dario Rossa ·

    Hi,to store historic data you

    Hi,

    to store historic data you may consider using financial peridos. You can create a batch of weekly financial periods in a few clicks with the latest releases. Regarding tho other questions, these coices are stricly dependent on the specific project you are managing.

    Dario

Log in or join to reply