Baseline New Activities
In the Open Standard
John SimsMember for 15 years 4 months
- Created
- 3
- 2
0
Hi,
I have just added some new activities to my project in P6, the orginal project was baselined and I'm wanting to update to some my new activities in the baseline budget.
The costs for the new actvities are showing in the budgeted labour cost but not in the BL project labour cost, what am i doing wrong?
This is the process i did:
Project/Mantain Baseline/Select latest Baseline/Update/Tick 'Add new activities and data' box/Update
Once update still no cost have been added to the BL Project labour cost coloumn i have set up.
Any ideas???
Thanks
John