Free Float higher than Total Float
In the Open Standard
Stefano BignozziMember for 19 years 4 months
- Created
- 2
- 2
0
Primavera did it again.
How can that Free Float is Higher than Total Float (for activities with Total Float >=0).
It is sufficient that, inside the schedule, you have some activities with negative Total Float.
Has anybody experienced the same problem and is Oracle going to fix it?