Budget at Completion vs Budgeted Expense Cost
In the Open Standard
Farzin FarsiMember for 17 years 11 months
- Created
- 1
- 1
0
Hi there,
In one of my many projects, I have a Budgeted Expense Cost for a selected activity (let’s say $500K) but Budgeted At Completion column is still zero.
I have more than 15 projects with almost the same structure with expense cost which do not have this issue (Budgeted At Completion is not zero).
Any one knows a solution for this?
I have checked all project properties and all are the same.
Regards
Farzin
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?