Completion and start dates on P6 schedule

Amir PezeshkMember for 14 years 10 months
Created
1
2
0

Hi,

For some reason the P6 installed on my laptop calculates start date as finish date completes.  For example:

Activity 1, Duration 4 days, Start January 2, 2012, Finish January 5, 2012 

Activity 2 Start must be January 6, 2012 since it's successor to the Activity 1, but the Activity 2 starts on January 5 same as finish date of .  This is happening on entire schedule.  I have checked User Preferences, and the Calender settings but i cann't understand where the problem is coming from.  Any idea?

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, Set the Working Time on

    Hi,

    Set the Working Time on your calendar and also show the time on the dates columns to be able to see the problem.

    Hope this will help.