Completion and start dates on P6 schedule
In the Open Standard
Amir PezeshkMember for 14 years 10 months
- Created
- 1
- 2
0
Hi,
For some reason the P6 installed on my laptop calculates start date as finish date completes. For example:
Activity 1, Duration 4 days, Start January 2, 2012, Finish January 5, 2012
Activity 2 Start must be January 6, 2012 since it's successor to the Activity 1, but the Activity 2 starts on January 5 same as finish date of . This is happening on entire schedule. I have checked User Preferences, and the Calender settings but i cann't understand where the problem is coming from. Any idea?
1 reply