Progress Updation
In the Open Standard
Arun VasanthMember for 17 years
- Created
- 3
- 2
0
Dear Friends
Me Completed one Base program.
As it is not a resourse loaded program I updated duration percentage.
Here starts the problem
Over all actual percentage it is showing .But Over all planned Percentage it is (Shedule percentage ) showing 0
only.In the attachment I shown two Planned Percentage
1 Performance percentage
2.Schedule Percentage
Friends please help to getout from this problem.
Please help me in showing Planned VS Actual Percentage
Over all and Activity wise....
Regards
Arun.V