Progress Updation

Arun VasanthMember for 17 years
Created
3
2
0

Dear Friends 

Me Completed one Base program.

As it is not a resourse loaded program I updated duration percentage.

Here starts the problem

 

Over all actual percentage it is showing .But Over all planned Percentage it is (Shedule percentage ) showing  0

only.In the attachment I shown two Planned Percentage 

1 Performance percentage 

2.Schedule Percentage 

 

Friends please help to getout from this problem.

Please help me in showing Planned VS Actual Percentage 

Over all and Activity wise....

Regards

Arun.V

3 replies

Oldest first
  1. 0
    Arun Vasanth ·

    Friends Awaiting your Valuble

    Friends Awaiting your Valuble reply....

  2. 0
    Raymund de Laza ·

    Arun, Make your program a

    Arun,

    Make your program a resource loaded and you will get what you requires.

  3. 0
    Arun Vasanth ·

    Thanks Raymund Is there any

    Thanks Raymund

     

    Is there any way with out loading resourse.....

     

     

     

    Regards

    Arun