Why when changing a resource does it change the 'Budgeted at completion' to equal the duration?

David SmithMember for 22 years 6 months
Created
2
2
0

When I manually change a resource, it changes the budgeted units to equal the duration on the activity.

what setting is doing this, i presume it is a tick box somewhere.

Can anyone please help?

Many thanks

Dave

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Dave, Make the Max Units/Time

    Dave,

    Make the Max Units/Time of the resource the same as the previous. 

    Hope this will help.

  2. 0
    Alfredo Jr. Hubilla ·

    Try go to the Projects

    Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..

     

    Hope this can help.

Log in or join to reply