"peak" function in P6 analytics ?
- Created
- 0
- 2
hi all,
P6 reporting being as good as it is, I'm planning on buying P6 Analytics instead of attempting to re-create the P3 "peak" function in Excel.
we currently use P6 v6.2.1, and the resource histogram only shows the "max" resource usage : if you have two tasks (FS linked, 200% resource), P6 will tell you that you need 400% resource for the day, instead of analyzing a bit further and telling that only a 200% peak is needed at a time.
does anyone know if P6 Analytics is capable of calculating resource usage like P3 used to ?
because all I can find is PDF/PPT files with little detail on real program functionnalities...
thanks in advance !