Resource Limits

Marty WeirMember for 14 years 7 months
Created
4
3
0

To my Friends

Can anyone please tell me whats going on with the attched picture.

How do i adjust the black limit line?

 

 

 

4 replies

Oldest first
  1. 0
    Daniel Limson ·

    HI Marty,Go to your Usage

    HI Marty,

    Go to your Usage Profile Icon and Click and then right click on the chart screen and select "usage profile options" then unclick where it says "Show Limit"

    Regards,

    Daniel

  2. 0
    Marty Weir ·

    Thanks Daniel   But i need to

    Thanks Daniel

     

    But i need to know how to adjust the limit.

    Cheers

    Martin

  3. 0
    Mike Testro ·

    Hi Marty Find the tasks with

    Hi Marty

    Find the tasks with the resources and move them about until the histogram drops below the limit - but keep within the available float.

    If the resources are on the critical path then you need to adjust your logic.

    Best regards

    Mike Testro

  4. 0
    Raymund de Laza ·

    Marty,On the Resource Pane,

    Marty,

    On the Resource Pane, select the resorce then go to Units & Prices then adjust adjust the max units /time accordingly.

     

    Hope this will help.

Log in or join to reply