Skip to content

Updating in progress activities in Primavera Contractor.

Tony SewellMember for 16 years 1 month
Created
1
1
0

Updating in progress activities in Primavera Contractor.

 

is there an easy way to update in progress activities without having to trial and error a % complete. I just want to progress the works as planned.

 

I know there is the update progress option but this then schedules the whole thing when you do it, I just want to record as-built up to data date before scheduling, similar to how activities are progressed without scheduling when you tick finished box.

 

Thanks

 

Tony

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    Hi Tony,There is a way,

    Hi Tony,

    There is a way, provided all activities are on schedule. You can drag the data date to your new cut-off date and this will highlight (yellow) all activities scheduled within that period and then choose update progress and this will update all highlighted activities as per plan.

    Regards,

    Daniel

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?