Progress bar against the baseline?

Ayman EleishMember for 15 years 9 months
Created
6
3
0

Dear All,

What is the easiest way to show the progress bar against the baseline?

Regrads,

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Ayman, Do you mean similar to

    Ayman,

    Do you mean similar to this?

  2. 0
    Ayman Eleish ·

    Raymund, I could not see the

    Raymund,

    I could not see the attached picture ,however I'd like to show the blue bar on the baseline bar as we used to get it from P3,on other words, to show the planned progress on the baseline bar.

    I am aware that it can be done by the user define fields,but it is lettle bit complicated,like to get an easy way.

    Thanks for reply,regards,

  3. 0
    Kashif Khan ·

    Hi,right click in the bar

    Hi,

    right click in the bar area,  select the baseline bar and close. you will see it.

    regrds,

    kk

  4. 0
    Raymund de Laza ·

    Ayman, Baseline Progress Bar

    Ayman,

    Baseline Progress Bar is not available in P6 in my opinion.

    However if you want to show using the UDF, create UDF say Min (From or Start Date) and Ali (To or Finish Date).

    On the bar option, create a Bar Name - BL Progress, Timescale - User Dates, then select the UDF for User Start Date and Use Finish Date. On the Bar Style - make the style & row the same as your baseline Bar.

    Hope this will help.

  5. 0
    Ayman Eleish ·

    Thanks Raymund, Actually I am

    Thanks Raymund,

    Actually I am doing that by using UDF and Global Chang taking into consideration that the finish progress bar shuold be based on the the schedule %.But I was looking for an easier way.

    Regards,

  6. 0
    Johannes Vandenberg ·

    Hi AymanI have inserted a

     

    Hi Ayman

    I have inserted a link to my website. Is this what you like to see?

    If so, and need more information let me know.

    http://plannenvoornietplanners.net/opgeven-van-de-voortgang/voortgang-week-4.html

     

    Johannes