Budgeted Cost

Abdullah MerchantMember for 15 years 10 months
Created
2
4
0

In my Project Schedule i have addded only Material and Non Labor resources. I am able to manually edit the Budgeted Cost field in the Activity Deatils tab. However since this is a entity that is calculated by multiplying the Budgeted Units with the Price/Unit then how is it that i am manually able to edit the Budgeted Cost field and the Budgeted Unit field do not change correspondingly.

For example:-

I have Pipes as a resouce with a Price/Unit of Rs.2500/meter.

I assigned this resource to an activity " Laying Bridge Rack CHW Pipes" and i estimated that 150 meters of pipe will be required for this activity.

So the Budgeted Cost = 2500 X 150=Rs. 375,000/-

 

But after i do this how am i still amble to manually edit the Bidgeted Cost field and then why does the Budgetd Units field remain unaffected after the change is done to the Budgeted Cost.

Am I  missing a setting ???????????????????? 

2 replies

Oldest first
  1. 0
    Mahmoud El Shamy ·

    hi abdullahwhat do you mean

    hi abdullah

    what do you mean by budget cost field

    please reply to make me help you

    thank you

  2. 0
    Kannan CP ·

    Abdullah, It is possible to

    Abdullah,

    It is possible to manually change the Budgeted Cost. But if you go to Tools......Recalculate Assignment Cost, cost will be in line with the Budgeted Units.

    Regards

    Kannan