Resource Usage Profile
- Created
- 0
- 3
Hi,
I developed one programme with labour units input (resource). While preparing the resource distribution month wise, it was working smoothly from Toools- Report Wizard. But not working properly with Resource spread sheet.
Problem in detail:
1. From Tools- Report wizard, I ticked the box for average and put the value as 30(to divide) to get a monthwise average
2. When I tried the same using the Resource Using profile and put the value as 30 its still showing the cumulative only.
For eg: 30 man days in a month. as average 1 person (Tools-Report wizard calculation)
same showing as 30 with repource profile (even with the average box ticked and value as 30)
Any ideas what may be wrong. I presume some tick box missing.
Regards
Kannan
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?