Changing Activity type for 3000+ Activities

John MaiuranoMember for 14 years 7 months
Created
2
1
0

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

2 replies

Oldest first
  1. 0
    Vaughn Edwards ·

    Perform a global. Where -

    Perform a global. 

    Where - Activity Type Equals Resource dependent

    Then Activity Type Equals Task dependent

    Click Change

  2. 0
    Muhammad Haziq ·

    the other easy way to change

    the other easy way to change the multiple activity type is..

    add another column into your p6 layout>add "activity type" column this code can be found under general category>change the first activity from "resource dependant" to "task dependant">select all the activity you want to change>right click and click fill down.

    for code type changing i usually use the fill down function because it much more easier and faster. hope this help

     

Log in or join to reply