Changing Activity type for 3000+ Activities

John MaiuranoMember for 14 years 7 months
Created
1
2
0

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

1 reply

Oldest first
  1. 0
    Usman Arshad ·

    John1- u can do it through

    John

    1- u can do it through global change

    2-u can add one column for Activity type and then change one activity type manually and crtl select other acitivites and press crt+E. this is like in excel we have crtl+d option.