start/finish dates in P6 v8.1

Kath MurrayMember for 14 years 11 months
Created
6
3
0

Hi

We have recently upgraded to Primavera 8.1 web version, its not been easy i had only just got used to P6 Enterprise. Anyway when i am creating projects or updating old ones and adding in relationships the start/finish dates are not moving unless i manually change them.

Can anyone please help im guessing its a setting i have but i cant find any info on this. I have the duration type set to fixed durations and units/time, i thought this might be the problem but it doesnt appear to be?

Thanks in advance

6 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Kath,You need to press F9

    Hi Kath,

    You need to press F9 to re-schedule or if you want automatic scheduling you need to tick that button in the scheduling options.

    Regards,

    Daniel

  2. 0
    Mohammed Ziaulla ·

    Hi,I have recently  installed

    Hi,

    I have recently  installed P6 on my laptop which has Windows 7...

     

    when i open the project i'm not able to see actvities of the programme all i can see is only WBS kindly help me out with this..

    i have attached screen shot for better understanding

  3. 0
    Kath Murray ·

    Thanks Daniel, i have been

    Thanks Daniel, i have been scheduling them (F9) but they seem to be pending when i check the status im really looking at how to force the scheduling without it pending, refreshing doesnt work.

     

    Mohammed, check if 'hide empty' is ticked or if there are any filters on clear them all.Hope that helps

  4. 0
    Kath Murray ·

    Hi Mohammed sorry i cant see

    Hi Mohammed sorry i cant see the screenshot i cant open the file

  5. 0
    Kath Murray ·

    Hi Mohammed sorry i cant see

    Hi Mohammed sorry i cant see the screenshot i cant open the file

  6. 0
    Mohammed Ziaulla ·

    i fixed this problem ......by

    i fixed this problem ......by changing the layout in actvity window(Highlited in Orange) 

     

Log in or join to reply