Wrong Budgeted Cost Calculation

Abdullah MerchantMember for 15 years 10 months
Created
0
4
0

Greetings,

Im having a tough time understanding the Budgeted Cost being wrongly dispalyed for an Activity which has a resource as follows:-

  • The Activity is 10 days in duration and set to " Fixed Duration and Unit"
  • The Activity and its Labor Resource"XYZ" both share the same 6 Days a week and 8 hours a day Calendar
  • The Labor Resource "XYZ" has a Price/Unit of Rs.100/hour
  • Only 1 Unit of Labor Resource "XYZ" is scheduled for each of the 10 days that make up the activity

So the Budgeted Cost of the Activity should be= Rs.100/hour X 8 hours (each day) X 10 days =  Rs. 8000

But my Budgeted Cost adds up to Rs. 1000..........thats it...........what am i missing????

Thi

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?