Skip to content

show progress bar on baseline

Kp RaoMember for 15 years 2 months
Created
2
2
0

Hi,

I assigned a baseline with progress to the current project.The baseline update is one month before the current project.

I want to show progress bar on baseline.

1.I want to show baseline progress percent complete in the current project.That is two bars are there.One is current bar with current progress and baseline bar.I want to show baseline progress bar.

2.Show current progress on the baseline bar.

Schedule percent complete bar is not as baseline percent complete.I dont want to show schedule percent complete.

Urgent help please.

kp

2 replies

Oldest first
  1. 0
    Abdullah Merchant ·

    Hi Kp,Are you saying that you

    Hi Kp,

    Are you saying that you want to show your Baseline bar and then show a separate bar above it that shows your actual progress? Because thats easy..............actually i have a little diffculty in understanding what you mean by baseline progress bar.....beacuse showing how far you have gone is tobe compared against your baseline and im sure youre aware of that it but showing the progress in your baseline is new for me too...

  2. 0
    Raymund de Laza ·

    Hi, So simple... transfer the

    Hi,

    So simple... transfer the row of progress bar in the same row of the baseline bar.

    Apply a different pattern and color.

    Hope this will help.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?