Problem with scheduling and durations
In the Open Standard
Mike LyonsMember for 19 years 7 months
- Created
- 6
- 3
0
Hi all,
I have inherited a program from a colleague which is based on 7day x 12hrs calendar.
When i am adding durations and relationships into the program, they seem to be extending past the dates required.
For example;
Activity 1 = 2 days
Activity 2 = 1 day (FS with ACT1) So total is 3 days.
However, what actually happens is Activity 1 takes 3 days and Activity 2 takes 2 days but the middle days overlap so i dont get a true picture.
Any help would be appreciated!
Kind Regards
Mike