Problem with relationships to completed/in progress tasks
In the Open Standard
Kate NashMember for 15 years 3 months
- Created
- 1
- 2
0
Hi
I hope this is a simple problem that can be easily fixed!
I have relationships to tasks in my project, however, when I set the task to started or finished, and then schedule the project, it seems to lose the relationship to the predecessor and seems to start on a seemingly random date
Is there an option I have to set to keep the relationships the same regardless of whether the activity is not started, in progress or completed?
Thanks!
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?