Problem with relationships to completed/in progress tasks

Kate NashMember for 15 years 3 months
Created
1
2
0

Hi

 

I hope this is a simple problem that can be easily fixed!

I have relationships to tasks in my project, however, when I set the task to started or finished, and then schedule the project, it seems to lose the relationship to the predecessor and seems to start on a seemingly random date

Is there an option I have to set to keep the relationships the same regardless of whether the activity is not started, in progress or completed?

Thanks!

1 reply

Oldest first
  1. 0
    Frederic Fasquelle ·

    Hi Kate,If there are links,

    Hi Kate,

    If there are links, they can not be deleted during schedule.
    If a logic is not respected, it must come from wrong links applied to your predecessors.
    Lets imagine that you have 3 activities in FS

    After your update, acitivty B is declared as completed while A is on going. Thus even if activity C is linked to B, it will not before completion of A.
    This could be one reason.


    Nevertheless, you can use "Mandatory contraint", but this clearly not a good practice in my mind.
    It is hidding your logic or mistake as identified here above,

    Regards