P6 Duration
In the Open Standard
Martin GomezMember for 16 years 5 months
- Created
- 2
- 2
0
Hi All
Please could someone help me .
I have set the calender to be 24h ,However if i have a duration of 1 day on the schedule it shows as finishing the following day . E.G if Activity A Duration =1 day , starts 1st April ,the finish date is shown as 2nd April.I understand that if i use the hour as the unit of measurement then i have to physicall y cahnge the finish time to 11.59.then it give me the result ,.is ther a way i can set the calender so that i do not have to do this physically always .Thanks in advance for your Help
2 replies
Oldest firstLog in or join to reply