I have defined header and footer for a project. The same header and footer reappears for all other projects opned thereafter.  Any suggestions to keep separate header and footer for different projects.

Thx in advance.

 

Regards,

Krish

1 reply

Oldest first
  1. 0
    Frederic Fasquelle ·

    Hi Krish,Reply is in your

    Hi Krish,

    Reply is in your question. For differents project, create differents layouts.

    Don't forget when you have change your layout to save it under different name, by using "Save as".
     

    Regards