"Add Variable" button under Page Setup ---> Text/Logo option for Header and Footer is not working

Ramesh KavasseryMember for 22 years
Created
3
2
0

 

Screenshot below. The "Add Variable" button does not work. What could be the problem ? Any settings to be changed ?

Also there is this character "ÿ" that appears on its own at the top of the Text/Logo block. What could be the reason ?

Has anybody experienced this ? Any feedback or suggestions is welcome. Thanks in advance.

BTW, the Page number fields were there as default, had not added them myself.

I use P6 Professional version 15.2.0 Build 15383.

 

 

3 replies

Oldest first
  1. 0
    Paul Epperson ·

    I have the same issue. Has

    I have the same issue. Has anyone figured out how to get the "Add Variable" button to work? Is it an admin preference setting? I can type in the header space, but cannot add the variable. I use P6 Professional version 15.1.

  2. 0
    Paul Epperson ·

    There is a work-around, you

    There is a work-around, you can type in the code for the variable you need, such as DD [data_date] for the data date. This will pull the data date and auto-populate for you. Same with ]project_id], [cd], [project_name], [layout_name], [filter_list], [page_number[, & [[total_pages]. 

     

    Does anyone know where to get a list of all the variables' code entries? 

  3. 0
    Rory Grant ·

    I know this post is 3 years

    I know this post is 3 years old but this may be useful for people experiencing the same problem 

     